The Great Stupa Time Line
1994 Consecrating The Great Stupa Site – Khensur Rinpoche
2000 Completion of Earthworks
http://inforescent.com/stupa173/images/pages/time-line/2000-Completion-of-Earthworks.jpg
2004 Aerial View Level 1
http://inforescent.com/stupa173/images/pages/time-line/2004-Aerial-View-Level-1.jpg
2005 Lama Zopa, Ian Green, Wayne Thompson and Peter Weiss Review Plans
http://inforescent.com/stupa173/images/pages/time-line/2005-Lama-Zopa-Review-Plans.jpg
2005 First Steel Columns Erected
http://inforescent.com/stupa173/images/pages/time-line/2005-First-Steel-Columns-Erected.jpg
2006 Level 2 steel and Shear walls
http://inforescent.com/stupa173/images/pages/time-line/2006-Level-2-steel-and-Shear-walls.jpg
June 2007 Blessing by His Holiness the Dalai Lama
2009 steel work to level 3
http://inforescent.com/stupa173/images/pages/time-line/2009-steel-work-to-level-3.jpg
2009 steel work and Shear walls to level 3
2010 massive trusses erected level 5- 6
http://inforescent.com/stupa173/images/pages/time-line/2010-massive-trusses-erected-level-5--6.jpg
June 2011 steel completed to level 4
http://inforescent.com/stupa173/images/pages/time-line/June-2011-steel-completed-to-level-4.jpg
June 2011 steel completed and pouring shear walls level 4
July 2011 concrete poured level 4
http://inforescent.com/stupa173/images/pages/time-line/July-2011-concrete-poured-level-4.jpg
September 2011 steel works to level 6 completed
December 2011 pouring shear walls level 5
http://inforescent.com/stupa173/images/pages/time-line/December-2011-pouring-shear-walls-level-5.jpg